Moorhead, Minn. (Valley News Live) The city of Moorhead says a major road construction project is over the halfway mark.

The city says the underpass project at Main Ave. and 20th and 21st St. S. is roughly 63% complete.

Construction is continuing on retaining walls and bridges during the winter, but underground utility work is on hold until the spring.

Crews hope to have the project finished by sometime in 2021.